Integrated Management of the Waters of Nestos/Mesta River Basin
Project Number: EUROPEAID/119665/D/SV/BG



Country: Bulgaria
Contracting Authority: The Ministry of Regional Development and Public Works
Contractor: Sogreah (France) and Project Managment Ltd (Ireland)
Beneficiaries: The West Aegean River Basin Direcorate, Blagoevgrad; The Ministry of Environment and Water; The West Aegean River Basin Council and The Ministry of Regional Development and Public Works
Contract Value: 400,000 Euro
Project Start Date: 01 December 2004
Project Duration: 12 Months
Overall Objectives:
The aim of this report is to provide a summary of the recommendation of the PHARE CBC Project “Integrated Management of the Waters of Nestos/Mesta River Basin South West Region Blagoevgrad District - Bulgaria”. The summary recommendations are presented in terms of the requirements for implementation of the EU Water framework Directive (2000/60/EC)
The contract objectives were in accordance with the requirements of the Water Framework Directive and recommendations of the Common Implementation Strategy guidance documents as follows:
- Detailed compilation and assessment of river basin characteristics and data based on the results of the Basin Overview prepared by the Western Aegean Basin Directorate for the Nestos/Mesta River Basin utilising basic modelling.
- Approval by the Nestos/Mesta Joint Coordination Committee (JCC) of a data model and GIS design.
- Strategic and management capacity building and support to the JCC.
- Data, technical and human resources gap analysis and identification of critical requirements to be met towards the implementation of the Water Framework Directive in the Nestos/Mesta river basin.
Project Results and Outputs:
- A detailed compilation and assessment, including basic modeling, based on the River Basin overview, of the basin characteristics.
- A proposal for a common data model and GIS design approved by the Joint Coordination Committee
- Technical capacity building and assessment of the staff of the West Aegean River Basin Directorate (WARBD).
- Strategic capacity building and operation and management support to the international JCC.
- Identification of specific gaps in data, technical and human resources critical for the further implementation of the requirements of the Directive (2000/60/EC) on the Nestos/Mesta river basin and identification of main and river basin management issues.
- Presentation of the Consultant’s findings and recommendations at minimum 2 seminars to the JCC and the WABRD.
Reports Produced for the Contracting Authority - MInistry of Regional Development and Public Works, Bulgaria:
- GIS Model Report
- River basin Characterisation Report
- Biological Assesssment
- Economic Analysis
- Point Source Modelling
- Data, Technical and Human Resource Gap Analysis
- Assessment of Technical and Administrative Capacity
- Strategic and Management Support to the Joint Coordination Committee
- Project Summary and Recommendations